• Skip to primary navigation
  • Skip to main content
  • Skip to footer
Pilbara Resources Group

Pilbara Resource Group

Connecting People Work & Community

  • Home
  • About PRG
    • What We Do
    • Experience, Excellence & Innovation
    • The PRG Leadership Team
    • Aboriginal Engagement & Employment
    • Quality, Health & Safety Environment
    • Vision & Values
  • Our Partners
    • NPJV
    • Bithari
    • Marapikurrinya Resources
    • Tjiwarl Contracting
  • PRG Services
    • Concept to Completion
    • Civil Works
    • Non-Process Infrastructure
    • Miscellaneous Mining Services
    • Training & Assessment
  • Projects
    • Wodgina Access Road
    • Permanent Facilities Installation
    • Site Facilities Installation & Services
    • Carlindi Camp Construction Project
    • Pippingarra Road Construction
  • News
  • Contact PRG

Permanent Facilities Installation

July 21, 2018 by Emily Reiffer

Project Details

Permanent Facilities Installation

Client:

MACA

Location:

Port Hedland WA Australia

Completion:

April 2018

Value:

AUD$410K

Scope:

Installation of Client Permanent Site Facilities

Gallery

Click to view full size image

Project Description

The MACA permanent facilities installation project outcome was the supply, installation & commissioning of the client site offices, crib room, ablutions, workshop sea containers and fuel supply facility at the Pilgangoora Lithium Mine Project. The facilities located 1.5 hours east of Port Hedland, are to service the client for the life of their contract.

The project scope of works encompassed the cranage, landing and complexing of the facilities and all associated plumbing and electrical works, including:

  • supply and installation of cable for power distribution using overhead servicing mounting
  • connection of generators for buildings & fuel tanks
  • testing and commissioning of all buildings
  • connection of water pumps to electrical outlets

The key challenge of the project was aligning with other client subcontractors working in a small area and ensuring all parties remained on schedule. NPJV fostered strong relationships with both the client and onsite subcontractors, allowing all project parties to plan and ensure all works affected by crossovers remained on schedule for the duration of the project.

This project demonstrated outstanding collaboration with the client and other subcontractors, leading to the project being completed on time, under budget and without incident.

Footer

Pilbara Resource Group

Head Office
Ground Floor, 10 Kings Park Road
West Perth
WA 6005

Phone: (08) 6424 8219

Email: info@pilbararg.com.au

Sitemap

  • Home
  • About PRG
  • Civil Works
  • Non-Process Infrastructure
  • Transport & Logistics
  • Miscellaneous Mining Services
  • Training & Assessment
  • NPJV
  • Marapukurrinya Resources
  • Bithari
  • Tjiwarl Contracting
  • Wodgina Access Road
  • Permanent Facilities Installation
  • Site Facilities Installation & Services
  • Carlindi Camp Construction Project
  • Pippingarra Road Construction
  • News
  • PO Terms & Conditions
  • Contact PRG

Contact PRG

  • This field is for validation purposes and should be left unchanged.

Copyright © 2025 Pilbara Resource Group · All rights reserved · website by Oracle Digital Marketing

Return to top